Scope of Work:
Installation of temporary safety netting (45 000 square meters) to allow for easy access to the roof area for the glass and painting contractors.

A crew of 20 rope access technicians have been present for the past 7 months.

Installation of 216 roof membrane panels, approx 45 000 square meters in total. The rigging and moving of temporary access platforms. The installation of gutter downpipes on the inside of the roof.

A crew of 110 rope access technicians were present for about 4 months.

The painting of the external steel facade, approx 36 000 square meters with International Paints products.

A crew of 80 rope access technicians and ground workers were present for 3 months

×

Hello!

Click one of our representatives below to chat on WhatsApp or send us an email to info@skysite.co.za

× How can we help you?